  1. On 8/18/2021 at 9:18 AM, MasterOmok said:

    18 cards Economy Tier with Subgrades

    Shipped: 02/08/2021        
    Delivered: 02/12/2021
    Received: 02/15/2021
    Scheduled for Grading: 07/07/2021
    Grading / Encapsulation / Imaging: 07/09/2021
    Grading / Quality Control: 08/10/2021
    Shipped: 08/11/2021
    In Hand: 08/17/2021

    Estimated Working Days (at submission): 60 days
    Estimated Working Days (at completion): 102 days + 5 days (sub grades) = 107 days 
    Actual Working Days: 124 days 
        178 calendar days – 54 days skipped:
            Excluded 25 Saturdays
            Excluded 25 Sundays
            Excluded 4 holidays:
            Presidents' Day (Monday, February 15, 2021)
            Memorial Day (Monday, May 31, 2021)
            Juneteenth (Friday, June 18, 2021)
            Independence Day (Monday, July 5, 2021)
     

    This is one of the best breakdowns of turnaround times I've seen! Thanks for the info.

  2. 3 hours ago, Ron Churches said:

    I had a 1 card w/subgrades express (part of a standard shipment) received 5/19. It's shipping today. That's 14 Biz days, taking out Memorial day.

    Still beats mine. 1 card Express with subgrades was delivered 4/30 and received 5/6. Still in "Grading/Quality Control". I called last Thursday and they said it would ship the next day, but I'm still waiting... 28 business days since delivered and 24 since received.

  3. I have an express submission delivered on 4/30 that has been sitting in grading since 5/18. I called this morning to see what was going on with it. I was told the payment had processed and it would be shipped by tomorrow.

    I'm thrilled to have it coming back soon, but I'm still curious as to why there was so much of a delay? Express turnaround times have been listed as 7-12 days during this time and my card has been at CGC for 24 business days, 12 days just for the grading step. It's almost at Standard turnaround times. If it has been there as long as a Standard submission, is there possibility of compensation for the extra cost of submitting Express over Standard since my card didn't really get graded at that speed?

  4. I'm having a tough time understanding the turnaround times and the updates that came through yesterday as it relates to my sub.

    4/30 - Express Sub was delivered to CGC

    5/6 - Sub was entered into system and updated to "received"

    5/13 - Sub was updated to "Scheduled for Grading"

    5/18 - Sub updated to "Grading/Quality Control"

    It makes sense that I haven't seen an update on the order if I consider the turnaround time that was posted through Monday of 24 days. However, now the estimated time was updated to 7 days. If that's accurate, why would my order still not be completed grading. I'm at 14 days from received. Am I not understanding turnaround times correctly? I do get that it's an estimate, but seems weird that they decreased the listed times (which is rare nowadays) and yet still have cards that are beyond that time.