18 cards Economy Tier with Subgrades

Shipped: 02/08/2021        
Delivered: 02/12/2021
Received: 02/15/2021
Scheduled for Grading: 07/07/2021
Grading / Encapsulation / Imaging: 07/09/2021
Grading / Quality Control: 08/10/2021
Shipped: 08/11/2021
In Hand: 08/17/2021

Estimated Working Days (at submission): 60 days
Estimated Working Days (at completion): 102 days + 5 days (sub grades) = 107 days 
Actual Working Days: 124 days 
    178 calendar days – 54 days skipped:
        Excluded 25 Saturdays
        Excluded 25 Sundays
        Excluded 4 holidays:
        Presidents' Day (Monday, February 15, 2021)
        Memorial Day (Monday, May 31, 2021)
        Juneteenth (Friday, June 18, 2021)
        Independence Day (Monday, July 5, 2021)
 

Edited by MasterOmok
Link to comment
Share on other sites

On 8/18/2021 at 9:18 AM, MasterOmok said:

18 cards Economy Tier with Subgrades

Shipped: 02/08/2021        
Delivered: 02/12/2021
Received: 02/15/2021
Scheduled for Grading: 07/07/2021
Grading / Encapsulation / Imaging: 07/09/2021
Grading / Quality Control: 08/10/2021
Shipped: 08/11/2021
In Hand: 08/17/2021

Estimated Working Days (at submission): 60 days
Estimated Working Days (at completion): 102 days + 5 days (sub grades) = 107 days 
Actual Working Days: 124 days 
    178 calendar days – 54 days skipped:
        Excluded 25 Saturdays
        Excluded 25 Sundays
        Excluded 4 holidays:
        Presidents' Day (Monday, February 15, 2021)
        Memorial Day (Monday, May 31, 2021)
        Juneteenth (Friday, June 18, 2021)
        Independence Day (Monday, July 5, 2021)
 

This is one of the best breakdowns of turnaround times I've seen! Thanks for the info.

Link to comment
Share on other sites

On 8/18/2021 at 9:18 AM, MasterOmok said:

18 cards Economy Tier with Subgrades

Shipped: 02/08/2021        
Delivered: 02/12/2021
Received: 02/15/2021
Scheduled for Grading: 07/07/2021
Grading / Encapsulation / Imaging: 07/09/2021
Grading / Quality Control: 08/10/2021
Shipped: 08/11/2021
In Hand: 08/17/2021

Estimated Working Days (at submission): 60 days
Estimated Working Days (at completion): 102 days + 5 days (sub grades) = 107 days 
Actual Working Days: 124 days 
    178 calendar days – 54 days skipped:
        Excluded 25 Saturdays
        Excluded 25 Sundays
        Excluded 4 holidays:
        Presidents' Day (Monday, February 15, 2021)
        Memorial Day (Monday, May 31, 2021)
        Juneteenth (Friday, June 18, 2021)
        Independence Day (Monday, July 5, 2021)
 

Thank you for the info. I will make sure to do the same when I receive mine from May.

Link to comment
Share on other sites

On 8/18/2021 at 7:18 AM, MasterOmok said:

18 cards Economy Tier with Subgrades

Shipped: 02/08/2021        
Delivered: 02/12/2021
Received: 02/15/2021
Scheduled for Grading: 07/07/2021
Grading / Encapsulation / Imaging: 07/09/2021
Grading / Quality Control: 08/10/2021
Shipped: 08/11/2021
In Hand: 08/17/2021

Estimated Working Days (at submission): 60 days
Estimated Working Days (at completion): 102 days + 5 days (sub grades) = 107 days 
Actual Working Days: 124 days 
    178 calendar days – 54 days skipped:
        Excluded 25 Saturdays
        Excluded 25 Sundays
        Excluded 4 holidays:
        Presidents' Day (Monday, February 15, 2021)
        Memorial Day (Monday, May 31, 2021)
        Juneteenth (Friday, June 18, 2021)
        Independence Day (Monday, July 5, 2021)
 

I don't even remember what I ate for dinner last night. VERY IMPRESSIVE!! lol. Thanks for the great breakdown. Gives us all an idea of true turnaround times.

Link to comment
Share on other sites

On 8/18/2021 at 10:18 AM, MasterOmok said:

18 cards Economy Tier with Subgrades

Shipped: 02/08/2021        
Delivered: 02/12/2021
Received: 02/15/2021
Scheduled for Grading: 07/07/2021
Grading / Encapsulation / Imaging: 07/09/2021
Grading / Quality Control: 08/10/2021
Shipped: 08/11/2021
In Hand: 08/17/2021

Estimated Working Days (at submission): 60 days
Estimated Working Days (at completion): 102 days + 5 days (sub grades) = 107 days 
Actual Working Days: 124 days 
    178 calendar days – 54 days skipped:
        Excluded 25 Saturdays
        Excluded 25 Sundays
        Excluded 4 holidays:
        Presidents' Day (Monday, February 15, 2021)
        Memorial Day (Monday, May 31, 2021)
        Juneteenth (Friday, June 18, 2021)
        Independence Day (Monday, July 5, 2021)
 

Heck of a breakdown, thanks!

My Standard (with subs) is on 81 working days today, went into grading/encapsulation/imaging since 07/29/2021. Hopefully I can beat the Economy numbers. Kind of wish I just sent them Economy now. 

Ok, gunna go cry now and wipe my tears with energy cards. 

Link to comment
Share on other sites

On 8/18/2021 at 1:42 PM, Keith Bradford said:

Heck of a breakdown, thanks!

My Standard (with subs) is on 81 working days today, went into grading/encapsulation/imaging since 07/29/2021. Hopefully I can beat the Economy numbers. Kind of wish I just sent them Economy now. 

Ok, gunna go cry now and wipe my tears with energy cards. 

Bulk is processing faster than economy now for the past month by 3-4 weeks..... Bulk is where it's at lol

Link to comment
Share on other sites

On 8/18/2021 at 12:42 PM, Keith Bradford said:

Heck of a breakdown, thanks!

My Standard (with subs) is on 81 working days today, went into grading/encapsulation/imaging since 07/29/2021. Hopefully I can beat the Economy numbers. Kind of wish I just sent them Economy now. 

Ok, gunna go cry now and wipe my tears with energy cards. 

In the same boat just a day later than you at 7/30, hopefully they finish up soon!

Link to comment
Share on other sites

Delivered 2/9/21
Received 2/12/21
Bulk (x 54) - Shipped 8/18, QC 8/16, Grading 7/8 
Bulk w Subgrades (x 9) - Shipped 8/18, QC 8/16, Grading 7/8
Economy w Subgrades (x 3) - Grading/Encapsulation/Imaging 7/8

Delivered 4/19/21 (didn't write ST on the box)
Received 7/12/21
Bulk (x 58) - Scheduled for Grading
Bulk w Subgrades (x 17) - Scheduled for Grading
Standard w Subgrades (x 7) - Shipped 8/3

Delivered 5/10/21 (didn't write ST on the box)
Received 8/9
Standard w/ Subgrades (x1) - Scheduled for Grading

Link to comment
Share on other sites

On 8/18/2021 at 6:58 PM, bsoken said:

Delivered 2/9/21
Received 2/12/21
Bulk (x 54) - Shipped 8/18, QC 8/16, Grading 7/8 
Bulk w Subgrades (x 9) - Shipped 8/18, QC 8/16, Grading 7/8
Economy w Subgrades (x 3) - Grading/Encapsulation/Imaging 7/8

Delivered 4/19/21 (didn't write ST on the box)
Received 7/12/21
Bulk (x 58) - Scheduled for Grading
Bulk w Subgrades (x 17) - Scheduled for Grading
Standard w Subgrades (x 7) - Shipped 8/3

Delivered 5/10/21 (didn't write ST on the box)
Received 8/9
Standard w/ Subgrades (x1) - Scheduled for Grading

Dang, my cards are still sitting as received since 3/12 with no movement. Granted, it's a larger order of 130 cards w/ subgrades but still. Roughly 107 working days per my quick calculation, initial estimated time of completion was 111 working days.

Link to comment
Share on other sites

My bulk finally switched to Grading/Quality Control!  It has officially taken the lead over my smaller economy submission, which was received the same day lol.

Bulk 198 cards:
Received - 2/12
Scheduled for Grading - 6/19
Grading/Encapsulation/Imaging - 7/9
Grading/Quality Control - 8/18
Finalized/Imaged/Shipped - N/A

Economy 7 cards
Received - 2/12
Scheduled for Grading - 6/19
Grading/Encapsulation/Imaging - 7/9
Grading/Quality Control - N/A
Finalized/Imaged/Shipped - N/A

Link to comment
Share on other sites

Economy submission 52 Cards 

Received 2/16

status grading incapsulating since about June 9th…. 
 

is this normal for my cards to be in the grading status for over 2 months?? I had another submission go into grading the same time for standard submission. I received those weeks ago, and nothing on my other submission. I reached out they told me about a week and it’s been 3-4 weeks. I messaged asking why it is well past 1 week and no update or return number now no reply? 
 

anyone else similar situation or did they lose my cards? Making sure before I take this further 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
9 9